The Supreme Court Rules on the Validity of Non-Liability Clauses in Commercial Contracts

The Supreme Court of Canada recently rendered an important decision which may have a significant impact on commercial contracts concluded under Quebec law. In the case of 6362222 Canada inc. v. Prelco inc., 2021 SCC 39, the Court was called upon to decide whether a limitation of liability clause could be set aside in virtue of the doctrine of breach of fundamental obligation.

The root of the problem: A poorly executed contract

In 2008, Prelco, a manufacturing company, retained the services of Créatech, a consulting firm, for the supply of software and professional services to improve its operating processes. The contract between the parties contained a limitation of liability clause:

Créatech’s liability to the client for damages that can be attributed to any cause whatsoever, regardless of the nature of the action, whether provided for in the agreement or delictual, shall be limited to amounts paid to Créatech under the Agreement unless such damages result from gross negligence or willful misconduct on Créatech’s part. If such damages result from the delivery of unsatisfactory services, Créatech’s liability shall be limited to the amount of any fees paid in relation to the said unsatisfactory services.

Createch may not be held liable for any damages resulting from the loss of data, profits or revenue or from the use of products or for any other special, consequential or indirect damages relating to services and/or material provided pursuant to the Agreement unless such damages result from gross negligence or wilful misconduct on Createch’s part. [par 11; Court’s translation]

The implementation of the system developed by Créatech contained numerous flaws. Prelco wearily terminated the contract in 2010 and entrusted another firm with the creation of a functional system.

Prelco took legal action against Créatech, claiming more than 6.2 million dollars for, amongst others, costs incurred to restore the system, and lost profits. Créatech invoked the above-mentioned clause in its defence.

Applicable law

Prelco argued that the limitation of liability clause was invalid, based on the doctrine of breach of a fundamental obligation in virtue of which a clause that exonerates or limits the liability of a party is ineffective if it sets aside the very essence of the obligation.

Non-liability clauses are in principle valid as they are based on the parties’ freedom to contract. However, in certain circumstances they are inoperative as a result of public order. One may not limit liability arising from intentional acts, gross negligence, bodily injury, or moral damages, pursuant to Article 1474 of the Civil Code of Québec [CCQ]. Similarly, according to Article 1437 CCQ, such clauses are inoperative in contracts of adhesion or consumer contracts.

In this case, the contract was freely negotiated by two at arms’ length sophisticated parties. A clause limiting a party’s liability could be stipulated.

The Court also addressed the argument of the requirement of reciprocity of obligations based on the premise that if a party is liberated from all of its obligations, the reciprocal nature of a contract is breached, contrary to the fundamental principle enshrined in Article 1371 CCQ.

The Court concluded that while the obligations of each party under the contract were unbalanced, the clause did not preclude reciprocity. Prelco was still entitled to keep the integrated system and to claim certain damages.

However, since the clause was valid, allowing Créatech to exclude some of its liability, Prelco could not be compensated for claims from customers, loss of profits on sales made and loss of profits on sales lost [par 104].

This case will certainly have an impact on commercial contracts, and on the freedom to negotiate clauses limiting liability and providing for damages which may claimed in case of non-performance.

337

Articles in the same category

No Notice of Default, No Termination

In Pavage Wemindji Inc. v. Compagnie de Construction et de Développement crie ltée, the Quebec Superior Court emphasized that a valid notice of default (mise en demeure) is not just a formality—it’s a precondition to exercising remedies like contract termination in many cases under Quebec civil law. The Decision The plaintiff, Pavage Wemindji Inc. (“Wemindji”), […]

Public Contracts: When Does a Penalty Clause Cross the Line?

Penalty clauses are a practical tool for owners: instead of having to prove actual losses when a contractor falls short, they can rely on a pre-agreed sum. For contractors, however, the stakes are equally significant — a lump-sum penalty can consume a substantial portion of the contract’s value. Still, the mechanism has its limits. Courts […]

Not So Intelligent!

Since the widespread adoption of artificial intelligence tools, growing concerns have emerged regarding their use in judicial proceedings. Recent decisions have relied on section 342 of the Code of Civil Procedure to sanction parties who make improper use of such tools. More specifically, this provision has been invoked on several occasions to address the use or citation […]

So? Is it settled or not?

In an interim decision in Djaferian v. Spanoudakis,rendered on February 20, 2026, the Superior Court had to determine whether an offer made 15 months earlier, prior to the institution of proceedings, could still be accepted and result in a transaction. Summary of Facts and Timeline The Plaintiff, a co-owner who sustained water damage to his private […]

Office Parties and the Employer’s Duty to Prevent Harassment

In De Sousa and Corporation interactive Eidos, 2026 QCTAT 4, the Quebec Administrative Labour Tribunal (ALT) appears to have broadened the scope of an employer’s obligation to prevent harassment. The decision arose from a complaint filed by a former employee who had been sexually assaulted at her home by a colleague following an office party organized by the […]

Should Economic Losses Be Considered Property Damage?

The Quebec Court of Appeal in Zurich, Compagnie d’assurances SA c. CRT Construction inc., recently overturned the Superior Court’s decision on the interpretation of a construction insurance policy. Facts CRT Construction Inc. (“CRT”) was retained by the City of Montreal (“City”) to perform major construction work at the Atwater water treatment plant. At the City’s request, CRT […]