Should Economic Losses Be Considered Property Damage?

The Quebec Court of Appeal in Zurich, Compagnie d’assurances SA c. CRT Construction inc., recently overturned the Superior Court’s decision on the interpretation of a construction insurance policy.

Facts

CRT Construction Inc. (“CRT”) was retained by the City of Montreal (“City”) to perform major construction work at the Atwater water treatment plant. At the City’s request, CRT obtained a construction insurance policy for this project with Zurich Insurance Company of Canada (“Zurich”). Given the project’s proximity to a water source and the nature of the work involved, CRT secured an additional endorsement covering flood-related damages that would otherwise have been excluded (“Endorsement”).

On November 12, 2017, a flood struck the job site. Cleanup and repairs ran from November 12, 2017, to March 28, 2018, causing significant project delays. Zurich agreed to cover site cleanup and repair costs in accordance with the Endorsement but refused to pay for indirect losses resulting from delays between November 12, 2017, and July 15, 2018, including additional salaries, per diems, and costs associated with extra work required.

Superior Court Decision

Zurich argued that the policy’s intent is to compensate for damages caused directly to the insured property because of its destruction or damage by one of the specified risks. Zurich added that the policy’s coverage is not meant to extend to economic losses such as loss of profits.

The Superior Court rejected this position. The Court determined that Zurich had to demonstrate that the additional amounts that it refused to pay were captured by an exclusion, which was not done. The Court further held that the Endorsement’s definition of “Loss” encompasses damages and losses caused directly or indirectly by a single event or a series of similar or connected events. In this case, the cause being the flood, both direct and indirect damages would be covered. As such, given Zurich’s agreement to compensate for direct damages to the insured property caused by the flood, CRT had a reasonable expectation that all resulting losses have been covered.

Court of Appeal Decision

The Court of Appeal applied the standard three step framework for interpreting insurance policies: (1) the insured must establish that the loss falls within the scope of coverage; (2) the insurer must then demonstrate that an exclusion applies; (3) the burden shifts again to the insured who must prove they are entitled to an exception to that exclusion.

The Court of Appeal found that the Superior Court erred at step one by failing to properly evaluate the scope of coverage provided by the flood Endorsement. The Endorsement is the instrument that granted coverage to the insured following the flood and should therefore be evaluated to assess the extent of coverage provided. In this case, the Endorsement explicitly limited coverage to losses and property damage cause directly to the insured property. The flood coverage therefore extended only to direct physical damage, not to all losses affecting the construction site itself, its profitability, or delays.

The Court also rejected the argument that the Endorsement’s definition of “Loss” expanded the scope of coverage. Definitions serve to apply specific policy provisions, such as those governing deductibles and limits of insurance. They do not define or extend the scope of coverage itself.

Take Away

The decision reinforces a critical principle, which is to analyze the scope of coverage first before turning to other policy provisions, definitions or exclusions. When a policy is designed to cover direct physical damage to insured property, indirect economic losses flowing from that damage are not automatically included. Further, policy definitions can clarify how certain provisions operate, but they cannot stretch coverage beyond its intended scope.

199

Authors

Articles in the same category

When it’s too late for latent defects…

The Superior Court recently rendered a judgment in Reinert v. Construction Maurice Bilodeau Inc., 2026 QCCS 2276, dealing with timeliness to give notice in cases of latent defects. The Facts In 2013, Ms. Sylvie Reinert and Mr. Denis Leclerc retained Construction Maurice Bilodeau Inc. (“CMB”) for the construction of a residential building on a vacant lot in Lévis. […]

Insurance Math: One Claim, Two Fires, Three Points of Origin, Zero Recovery: When Circumstantial Evidence Speaks Louder Than a Confession

In Chatel v. Desjardins Insurance, 2026 QCCS 712, the Quebec Superior Court reaffirmed a principle of insurance law: direct evidence is not required to establish an intentional fault. Mr. Chatel claimed $532,000 under his homeowner’s insurance policy following two fires that occurred four days apart. The first caused partial damage to his residence, while the second […]

The Quarrelsome Litigant: When the Right to Sue Becomes a Scourge

Access to the courts is a fundamental right, but what happens when a person uses it not to assert legitimate rights, but to harass others or clog the system to excess? This is quarrelsomeness: the tendency to exercise one’s right to litigate in an excessive or unreasonable manner. Far from being a marginal phenomenon, it […]

Before Buying a Product, Read This: The Rules Are Changing on October 5!

On October 5, 2026, the final amendments to the Regulation amending the Regulation respecting the application of the Consumer Protection Act (the “Regulation“) are expected to come into force, completing the implementation of the new “good working order” warranty in the province of Quebec. When this warranty applies, the merchant or manufacturer will be required to repair […]

No Notice of Default, No Termination

In Pavage Wemindji Inc. v. Compagnie de Construction et de Développement crie ltée, the Quebec Superior Court emphasized that a valid notice of default (mise en demeure) is not just a formality—it’s a precondition to exercising remedies like contract termination in many cases under Quebec civil law. The Decision The plaintiff, Pavage Wemindji Inc. (“Wemindji”), […]

Public Contracts: When Does a Penalty Clause Cross the Line?

Penalty clauses are a practical tool for owners: instead of having to prove actual losses when a contractor falls short, they can rely on a pre-agreed sum. For contractors, however, the stakes are equally significant — a lump-sum penalty can consume a substantial portion of the contract’s value. Still, the mechanism has its limits. Courts […]